Phoenix Mill & Tailings Project

Our scope of work at this 40,000 tpd gold mill included construction of the concentrate storage building, electrical buildings, pebble crushing circuit, tailings underdrain system, decant piping and reclaim water pump station.

We also provided personnel for start-up assistance and are under contract for on-going plant maintenance.



Lisbon Valley SX/EW Plant

Work on this project generally consisted of disassembly, identification, cataloging, transportation, offloading and reassembly of the Equatorial SX/EW plant facilities from Tonopah, Nevada to the Lisbon Valley Mine near Moab, Utah.

Areas included crushing, conveying, stacking, heap leach, solution collection, reagents, solvent extraction, electrowinning, and plant utilities.

Work included approximately 7,000 cubic yards of concrete foundations, 1,500 tons of structural steel erection, a 2,500 tph gyratory crusher, secondary crushing and screening area, stacking system, SX/EW plant and 35,000 lineal feet of process piping.



Pend Oreille Mine Lead Concentrator

We performed both underground and surface construction required to re-commission the Pend Orielle Mine near Metaline Falls, Washington.

The underground scope of work included refurbishment and installation of the primary and secondary crushers and approximately 6,000 lineal feet of conveyor to surface.

On surface we refurbished and installed the tertiary crushing system and the primary and regrind mills. We also installed the flotation and filter systems complete through the tailings pumps and tailings pipeline.

Work included concrete foundations, steel erection, mechanical installation, process piping, electrical and instrumentation.



Cripple Creek & Victor Gold Mine Cresson Expansion Project

Work entailed several contracts as part of a major expansion, including the Truck Shop Civil and Mechanical, the Crusher Expansion Project and the ADR Expansion Phase I and II.

The Crusher Expansion Project was especially challenging given the scope of work required the placement of 4,500 cubic yards of concrete, 5,400 tons of structural steel and plate work, a gyratory crusher, three cone crushers and 2,100 lineal feet of conveyors and miscellaneous equipment at an elevation of 10,000 feet during winter conditions in the Colorado Rockies.

This project earned us the prestigious Gold Hard Hat Award from McGraw-Hill Companies, Colorado Construction in 2002.



Underground Plant Facilities

In addition to surface facilities Schmueser & Associates, Inc. has constructed underground plant facilities.


Underground Conveyor installation at the Pend Oreille Mine.


Ductwork installation for underground crushing facilities at the Pend Oreille Mine.


Mohawk Lift and lube piping in a maintenance bay at Turquoise Ridge Mine.


Belt feeder underground at the Deep Post Mine.